Designing
and constructing a pipeline is a major undertaking, requiring a wide
variety of engineering and construction skills. A large pipeline the operator would have the internal resources (both trained and
experienced manpower and equipment) to undertake all phases of
pipeline construction, it is more likely that virtually all of the
major phases of construction will be contracted out to companies
possessing the necessary expertise and capacities to complete the
task. While that guarantees the critical requirements of the pipeline
construction will be met, it also introduces the need to control
logistics to ensure that all contractor activities are coordinated
and not mutually exclusive of one another. Construction can take
place because pipeline construction equipment is distributed along
the pipeline route in a moving assembly line in which only one major
item of construction equipment is normally needed at any one point of
time. The distance along the pipeline over which this equipment is
deployed is relatively shorter and less than a mile, but there may be
several sets of construction equipment operational along the pipeline
route at any given time. The complete set of equipment — for
ditching, welding, coating, lowering in, and backfilling are called
spreads. A single pipeline may be built using several spreads,
reducing the overall construction period, but also increasing the number of people and secondary resources required to support them.
Large pipeline projects can also be divided into two or more
segments, and different construction contractors may be used to
install each segment. Various construction activities also take place
simultaneously on a number of segments. Each of these contractors may
field several spreads to build a segment. The actual installation of
the pipeline includes these major steps:
1. clearing the ROW as
needed.
2. Ditching.
3. Stringing pipe joints along the ROW.
4.
Welding the pipe joints together.
5. Applying a coating and wrapping
the exterior of the pipe (except for the portions of the pipe at
each end, which is sometimes coated before being delivered to the job
site).
6. Lowering the pipeline into the ditch.
7. Backfilling the
ditch.
8. Testing the line for leaks.
9. Cleanup and drying the
pipeline after testing to prepare it for operation.
10. Reclaiming
impacted environmental areas.
No comments:
Post a Comment